Example document

Example SWMS: residential rooftop solar installation (NSW)

This is a finished Safe Work Method Statement, start to finish — 9 job steps, 27 hazards, risk ratings before and after controls, and a worker sign-on sheet. It was built with the same guided builder you'd use, and you can download the PDF for free.

This is a worked example, not a real job. The company, ABN, site address, workers and licence numbers are all fictional. Copy the structure — never the content: your SWMS has to describe your site, your crew and your work method, and it must be reviewed by a competent person before work starts.

Create my own SWMS

Safe Work Method Statement

Residential rooftop solar installation SWMS

SWMS-2026-104 · Version 3 · NSW work health and safety laws

SWMS GeneratorAustralia

Southern Cross Solar & Electrical Pty Ltd

ABN 11 000 000 011

1. Project and company details

Project
Seven Hills rooftop PV — 6.6 kW
Site address
27 Kestrel Rise, Seven Hills NSW 2147
Client
N. and A. Petrakis (homeowners)
Principal contractor
Southern Cross Solar & Electrical Pty Ltd
Work activity
Residential rooftop solar installation
Trade
Solar
Dates
2026-08-25 to 2026-08-26
Site supervisor
Dan Whitmore
Prepared by
Dan Whitmore
Company contact
(02) 5550 7412 · site@southerncrosssolar.example

2. Scope of work

Supply and installation of a 6.6 kW grid-connect photovoltaic system on a single-storey residence: 16 x 415 W modules on a Colorbond roof at 22 degrees pitch, 4.8 m from ground level to the gutter line. Work covers roof access and edge protection, rail-mounted racking with sealed roof penetrations, two DC strings run to a 5 kW string inverter on the garage wall, AC connection at the existing main switchboard on a dedicated solar circuit with DC and AC isolators, then testing and commissioning to AS/NZS 5033 and AS/NZS 3000. A Certificate of Compliance for Electrical Work is issued at handover and the grid connection application has already been lodged with the network distributor. This SWMS is prepared under Part 6.3 of the Work Health and Safety Regulation 2017 (NSW) because the work involves two categories of high risk construction work: a risk of falling more than two metres, and work on or near energised electrical installations.

3. High-risk construction work

  • Risk of falling more than 2 metres
  • Work near energised electrical installations

4. Workers and competencies

NameRoleLicence / ticketExpiry
Dan WhitmoreSite supervisor / Licensed electricianNSW Electrical Licence · CEC Grid-Connect Design & Install (EL-284416C)2028-03-31
Priya RamanSolar installer / First aid officerCEC Accredited Installer · Work Safely at Heights (RIIWHS204E) · HLTAID011 Provide First Aid (CEC-A118204)2027-11-30
Josh TuiletufugaSolar installerGeneral Construction Induction (White Card, CPCWHS1001) · Work Safely at Heights (RIIWHS204E) (WC-0459 2213)
Mia Chen3rd-year apprentice electrician (direct supervision)NSW Apprentice Electrician · General Construction Induction (White Card) (AP-771902)

5. Site conditions

ConditionAnswerDetails
Is the site occupied?yes
Will the public be present?yes
Is traffic management required?no
Are overhead power lines present?yes
Is underground infrastructure present?N/A
Is work performed at height?yesHeight of work: 4.8 m to the gutter line; Colorbond roof at 22 degrees pitch; Access method: Ladder; Fall protection: Guard rails
Are hazardous substances used?no
Is mobile plant operating nearby?no
Is weather exposure relevant?yes
Are there restricted access areas?yes

6. Job steps, hazards, risk ratings and control measures

9 steps · 27 hazards identified

Step 1: Arrive and inspect site

Hazard

Slips, trips and uneven ground on the side access path used to carry gear

Responsible: Dan Whitmore

Control measures

  • Administrative controlsWalk the full access route at the pre-start and agree one path in and out
  • Engineering controlsClear and cone the path; nothing is left lying across it during the day
  • PPELace-up safety boots with slip-resistant soles worn on site at all times

Initial

Medium

Residual

Low

Hazard

Bonded asbestos (ACM) sheeting disturbed in the eaves of a pre-1990 dwelling while running cable

Responsible: Dan Whitmore

Control measures

  • EliminationStop work: nothing is drilled, cut or broken in any sheet suspected of containing asbestos
  • Administrative controlsAny pre-1990 eaves or wall sheet is presumed to be ACM until a licensed assessor says otherwise
  • Administrative controlsLicensed asbestos removalist engaged; work in that area resumes only on written clearance
  • PPEP2 respirator and disposable coveralls if incidental contact cannot be avoided while withdrawing

Initial

High

Residual

Medium

Hazard

Worker starts on site without a verified ticket or without being briefed on this SWMS

Responsible: Dan Whitmore

Control measures

  • Administrative controlsLicences and tickets sighted and recorded before anyone touches a tool
  • Administrative controlsThis SWMS is read and signed by every worker at the pre-start meeting
  • Administrative controlsThe apprentice works within sight and sound of the licensed electrician all day

Initial

Medium

Residual

Low

Step 2: Set up exclusion area

Hazard

Householder or passer-by struck by a dropped tool, fixing or module

Responsible: Priya Raman

Control measures

  • Isolation3 m mesh-fenced exclusion zone directly below the work area, signed and kept closed
  • Engineering controlsTool lanyards on everything carried onto the roof; fixings kept in a closed catch bag
  • Administrative controlsHouseholder briefed at the pre-start on which doors, paths and windows are out of use today

Initial

High

Residual

Low

Hazard

Vehicle and pedestrian conflict while unloading modules at the kerb

Responsible: Josh Tuiletufuga

Control measures

  • Engineering controlsCones out and a spotter walking the ute back into the driveway
  • Administrative controlsUnload on the property side; modules are never staged across the footpath
  • PPEHigh-vis worn from the moment the vehicle stops until it leaves

Initial

Medium

Residual

Low

Hazard

Children or pets entering the drop zone during the day

Responsible: Priya Raman

Control measures

  • Administrative controlsConfirm with the householder that pets are secured indoors before the ladder goes up
  • IsolationSide gate closed, latched and signed for the duration of the works
  • Administrative controlsAll work above stops immediately if anyone enters the zone, and does not restart until it is clear

Initial

High

Residual

Low

Step 3: Access roof

Hazard

Fall from the roof edge — 4.8 m to the gutter line (high risk construction work)

Responsible: Dan Whitmore

Control measures

  • Engineering controlsPerimeter guard rail installed to both working edges before any worker steps onto the roof
  • Administrative controlsWhere rail cannot be fixed at the hip, a roof anchor and full-body harness in fall restraint, lanyard set short of the edge
  • Administrative controlsNo work within 2 m of an unprotected edge under any circumstances
  • PPEHarness and lanyard inspected and tagged before each use; damaged gear is destroyed, not returned to the ute

Initial

Extreme

Residual

Medium

Hazard

Ladder slips, is over-reached from, or is climbed while carrying materials

Responsible: Josh Tuiletufuga

Control measures

  • Engineering controlsIndustrial 150 kg rated ladder, tied off at the stiles and extending 1 m above the gutter
  • Administrative controlsSet at a 4:1 pitch on firm level ground, clear of the drop zone and any door swing
  • Administrative controlsThree points of contact; nothing is carried up or down by hand

Initial

High

Residual

Low

Hazard

Foot through a fragile skylight or brittle roof sheet

Responsible: Dan Whitmore

Control measures

  • Engineering controlsSkylight covered with a load-rated cover, fixed down and marked before roof work starts
  • Administrative controlsWalk the purlin lines only; never traverse the middle of an unsupported sheet
  • Administrative controlsSkylight and penetration locations identified at the pre-start walk and flagged

Initial

High

Residual

Medium

Step 4: Deliver materials to work area

Hazard

Manual handling injury lifting a 22 kg module overhead from ladder height

Responsible: Priya Raman

Control measures

  • SubstitutionInclined panel hoist used for every module; no module is hand-passed up the ladder
  • Administrative controlsTwo-person lift on the roof, module kept below shoulder height and close to the body
  • PPEGrip gloves worn for all module handling

Initial

High

Residual

Low

Hazard

Load dropped from roof level into the area below

Responsible: Josh Tuiletufuga

Control measures

  • IsolationExclusion zone stays closed and unattended for the whole time anything is being lifted
  • Engineering controlsHoist rated for the load and inspected before use; load secured on the roof before the sling is released
  • Administrative controlsNothing is lifted over an occupied area; a spotter stays at ground level for every lift

Initial

High

Residual

Low

Hazard

Wind gust catches a module and turns it into a sail at height

Responsible: Dan Whitmore

Control measures

  • EliminationNo module is lifted, carried or placed once wind exceeds 40 km/h — work stops
  • Administrative controlsBureau of Meteorology forecast checked at the pre-start and re-checked after lunch
  • Administrative controlsModules laid flat and strapped on the roof, never left leaning or standing on edge

Initial

High

Residual

Medium

Step 5: Install mounting system

Hazard

Fall while working near the eaves fixing rail and flashing penetrations

Responsible: Dan Whitmore

Control measures

  • Engineering controlsGuard rail remains in place for the entire rail installation, not just the first course
  • Administrative controlsRestraint lanyard adjusted so the worker physically cannot reach the edge
  • Administrative controlsNever lean past the rail to reach a fixing — the rail is moved instead
  • PPEFull-body harness worn and clipped for all work outside the rail line

Initial

Extreme

Residual

Medium

Hazard

Cuts, struck-by and burns from rail offcuts, fixings and hot Colorbond sheeting

Responsible: Josh Tuiletufuga

Control measures

  • Engineering controlsRail cut and deburred on the ground, not on the pitch
  • Administrative controlsTools and fixings kept in a closed bag; nothing loose is left on the roof
  • PPEGloves, safety glasses and long sleeves worn for all rail work

Initial

Medium

Residual

Low

Hazard

Heat stress and UV exposure working on an exposed metal roof

Responsible: Priya Raman

Control measures

  • EliminationRoof work rescheduled outside 11:00–15:00 whenever the forecast exceeds 35 °C
  • Administrative controls600 ml of water per person per hour, shaded rest rotation every 45 minutes, buddy checks for heat symptoms
  • PPEUPF 50+ long sleeves, broad-brim hat under the hard hat and SPF 50+ sunscreen reapplied every two hours

Initial

High

Residual

Low

Step 6: Install solar panels

Hazard

DC electric shock — modules are live the moment they see daylight, up to about 600 V string voltage (high risk construction work)

Responsible: Dan Whitmore

Control measures

  • IsolationModules stay covered and string ends stay capped until the final connection is made
  • Engineering controlsMC4 connectors only, mated dry and clicked home; 1000 V DC-rated insulated tools used throughout
  • Administrative controlsOnly the licensed electrical worker makes or breaks a DC connection — never the apprentice
  • PPEClass 0 insulating gloves worn for all DC connection work

Initial

Extreme

Residual

Medium

Hazard

Fall while positioning and clamping modules along the roof edge

Responsible: Dan Whitmore

Control measures

  • Engineering controlsGuard rail stays up for the whole module install
  • Administrative controlsModules landed onto the rail from above; nobody carries a module along the edge
  • Administrative controlsRestraint lanyard clipped and length-checked before each row is started

Initial

Extreme

Residual

Medium

Hazard

Crush or pinch injury between the module frame and the rail

Responsible: Priya Raman

Control measures

  • Administrative controlsAgreed lift-and-lower calls between the two installers on every module
  • Engineering controlsClamps started by hand and only then finished with the torque driver
  • PPEGloves worn for all module placement

Initial

Medium

Residual

Low

Step 7: Electrical connection

Hazard

230 V electric shock working at the main switchboard (high risk construction work)

Responsible: Dan Whitmore

Control measures

  • IsolationMain switch locked out with a personal padlock and danger tag; the key stays with the person doing the work
  • Administrative controlsTest before you touch — prove the tester on a known live source before and after every test
  • Administrative controlsNo live work. If the board cannot be isolated, work stops and the network distributor is called
  • PPEInsulated gloves and 1000 V rated hand tools for all switchboard work

Initial

High

Residual

Medium

Hazard

Arc flash while terminating the solar circuit into the switchboard

Responsible: Dan Whitmore

Control measures

  • IsolationBoard de-energised and proven dead before any termination is started
  • Engineering controlsDedicated solar circuit breaker with DC and AC isolators installed to AS/NZS 5033
  • Administrative controlsOne worker at the board at a time; the apprentice observes from outside the arc zone
  • PPEFace shield and natural-fibre long sleeves — no synthetics near the board

Initial

High

Residual

Medium

Hazard

Contact with the overhead LV service mains at the point of attachment

Responsible: Dan Whitmore

Control measures

  • Administrative controls3 m exclusion maintained from the service mains, per the SafeWork NSW code of practice for work near overhead power lines
  • Administrative controlsNo conductive material — rail, ladder, module or cable draw — is moved within that zone
  • Engineering controlsCable route planned at the pre-start to stay on the far side of the roof from the service
  • Administrative controlsIf an approach is unavoidable, a dedicated safety observer is posted and the distributor is asked to fit temporary covering

Initial

High

Residual

Medium

Step 8: Testing and commissioning

Hazard

Unexpected re-energisation while a worker is still on the array

Responsible: Dan Whitmore

Control measures

  • IsolationOne nominated person holds the isolation key and is the only person who removes the tag
  • Administrative controlsVerbal all-clear taken from every worker by name before anything is switched on
  • Administrative controlsLockout stays on until the roof is confirmed clear of people and tools

Initial

High

Residual

Medium

Hazard

Fall while verifying array polarity and clamp torque on the roof

Responsible: Priya Raman

Control measures

  • Engineering controlsGuard rail stays up until every rooftop check is signed off
  • Administrative controlsAll rooftop testing is scheduled before edge protection comes down, never after
  • PPEHarness worn in restraint for any check outside the rail line

Initial

Extreme

Residual

Medium

Hazard

Mislabelled isolators leave a latent shock risk for the next worker on the property

Responsible: Dan Whitmore

Control measures

  • Engineering controlsAS/NZS 5033 shock-hazard and isolation signage fitted at the array, the inverter and the main switchboard
  • Administrative controlsCertificate of Compliance for Electrical Work issued and all test results recorded
  • Administrative controlsHomeowner walked through the emergency shutdown procedure at handover

Initial

High

Residual

Low

Step 9: Site clean-up

Hazard

Fall while dismantling edge protection — the last task of the day and the one most often rushed

Responsible: Dan Whitmore

Control measures

  • Administrative controlsEdge protection comes down last, worked from the ladder or from inside the rail line — never by leaning out
  • Administrative controlsDismantling is a planned task with its own toolbox talk, not something started after the crew has been told to knock off
  • PPEHarness stays on and clipped until the last rail section is off the roof

Initial

High

Residual

Medium

Hazard

Screws, offcuts and packaging left in gutters, driveway and lawn

Responsible: Josh Tuiletufuga

Control measures

  • Engineering controlsMagnet sweep of the driveway, lawn and path before the ute is loaded
  • Administrative controlsGutters cleared and photographed as part of the handover pack
  • Administrative controlsAll packaging and offcuts removed from site the same day

Initial

Medium

Residual

Low

Hazard

Manual handling injury during load-out at the end of a hot day

Responsible: Priya Raman

Control measures

  • SubstitutionTrolley used for the panel hoist and the ladder
  • Administrative controlsLoad out in pairs, heaviest items first while the crew is still fresh
  • PPEGloves and boots worn until the vehicle is loaded and closed

Initial

Medium

Residual

Low

7. Personal protective equipment

  • Hard hat
  • Safety boots
  • High-vis clothing
  • Safety glasses
  • Gloves
  • Harness
  • Long-sleeve UPF 50+ shirt, broad-brim hat and SPF 50+ sunscreen
  • Class 0 insulating gloves (DC connections)

8. Plant, equipment and maintenance

ItemPre-use inspectionLicence requiredTraining / competency
Industrial extension ladder (150 kg rated)YesNoNo
Temporary perimeter edge protection (guard rail system)YesNoYes
Roof anchors, full-body harness and trauma-relief strapsYesNoYes
Inclined panel hoistYesNoYes
Cordless power tools and calibrated torque driverYesNoNo
1000 V insulated hand toolsYesNoNo
Calibrated insulation resistance tester and two-pole voltage testerYesYesYes
Lockout/tagout kit and personal danger tagsNoNoYes
2 kg CO₂ extinguisher and Type B first aid kitYesNoNo

9. Emergency procedures

Emergency contact
000 (Police / Fire / Ambulance), then Dan Whitmore — site supervisor — 0491 570 156
First aid officer
Priya Raman — HLTAID011 Provide First Aid, current to 30/11/2027
First aid kit
Type B kit in the rear canopy of the work ute, parked in the driveway
Assembly point
Front nature strip at the letterbox, clear of the exclusion zone and the driveway
Nearest medical facility
Blacktown Hospital, 18 Blacktown Road, Blacktown NSW 2148 — approximately 9 minutes by road
Emergency equipment
2 kg CO₂ extinguisher, 6 m rescue ladder, trauma-relief straps fitted to every harness, eye wash, and a charged mobile phone carried by the supervisor

Suspension trauma rescue plan: never leave a worker hanging in a harness. Raise the alarm and call 000 immediately, deploy the trauma-relief straps fitted to every harness so the worker can take their weight on their legs, and recover them to the roof or the ground within 10 minutes using the 6 m rescue ladder. Do not lay a recovered worker flat — keep them seated and hand over to paramedics. Notifiable incidents: any death, serious injury or dangerous incident — including a fall from height, an electric shock, or an uncontrolled descent of plant or material — must be reported to SafeWork NSW on 13 10 50 immediately, and the incident site must not be disturbed beyond what is needed to make it safe or to help an injured person.

10. Monitoring and review

  • This SWMS is reviewed with all workers at the daily pre-start meeting.
  • Work stops and the SWMS is revised if conditions change or a new hazard appears.
  • The person responsible for reviewing control measures is Dan Whitmore.
VersionDateAuthorChange
12026-07-28Dan WhitmoreInitial SWMS prepared for the Seven Hills rooftop PV installation.
22026-08-11Dan WhitmoreSite inspection: overhead service mains exclusion added; edge protection upgraded from harness-only to perimeter guard rail.
32026-08-19Priya RamanReviewed at pre-start; heat management controls added for forecasts above 35 °C.

11. Worker sign-on

All workers must sign to confirm they have read, understood and will follow this SWMS.

NameRoleSignatureDate
Dan WhitmoreSite supervisor / Licensed electrician___/___/____
Priya RamanSolar installer / First aid officer___/___/____
Josh TuiletufugaSolar installer___/___/____
Mia Chen3rd-year apprentice electrician (direct supervision)___/___/____
Users are responsible for reviewing and adapting the SWMS to the actual worksite, work methods and applicable regulatory requirements before work begins.

This was built in about five minutes

You answer questions about the job — trade, site, crew, plant — and the builder suggests the job steps, hazards and controls that apply, then you edit anything that doesn't match your method.

  • Built for Australian WHS requirements, state by state
  • Preview every section before you pay a cent
  • Site-specific — never a blank template

A$19.90 per document, or A$29/month for 10 — you only pay when you download.

What goes in each section

  1. 1. Project and company details — who is doing the work, where, and for whom
  2. 2. Scope of work — the method, in enough detail that a stranger could follow it
  3. 3. High-risk construction work — which of the 18 categories apply
  4. 4. Workers and competencies — names, roles, licences and expiry dates
  5. 5. Site conditions — what is actually happening on this site on the day
  6. 6. Job steps, hazards, risk ratings and control measures — the heart of the document
  7. 7. Personal protective equipment
  8. 8. Plant, equipment and maintenance
  9. 9. Emergency procedures — including the rescue plan for work at height
  10. 10. Monitoring and review — plus the version history